Which of the following statements are True with respect to sprint planning?

Which of the following statements are True with respect to sprint planning?

a.For sprint backlog creation, user stories are broken down into its constituent tasks

b.The sprint backlog cannot be changed once the sprint has started

c.The sprint Backlog is a living artifact and is updated on a daily basis

d.The tasks that are not completely done at the end of the sprint are always moved to next sprint backlog

 

Answer:- The correct option is C). The sprint Backlog is a living artifact and is updated on a daily basis

Sprint planning in agile methodology is an event that starts every sprint where the team outlines what all work will be done during this particular sprint. The sprint backlog is another important output of the sprint planning. Unlike the whole product backlog which is defined from the beginning and does not change, sprint there are many changes after it has commenced.

During sprint planning, the team choose user stories from the product backlog and also splits them into separate tasks that will be finished in a sprint. These tasks are included in the sprint backlog. But, the sprint backlog is not concluded at the start of a sprint. It is meant to be a dynamic, lifelong document that gets revised every day. Team members can modify, add or remove tasks on the sprint backlog as work advances to indicate in real time how a given sprint is changing. Closed tasks are updated, and new blocking ones that appear on the way are added. Flexible sprint backlog involves working collaboratively and inspecting regularly so that the changing priorities can be tracked to ensure the wind up of sprint goal.